Solar Installation Karachi handles net metering in Karachi from start to finish. We check your sanctioned load, design your system to fit the current rules, prepare your documents, submit the application to K-Electric, follow it through review and track it until your bidirectional meter is installed.
Last reviewed: October 2026
In February 2026, NEPRA replaced the old net metering rules with the Prosumer Regulations 2026. K-Electric now processes new applications as net billing. Most people still call it net metering in Karachi, so we use both terms on this page.
For new applicants, the main changes are:
These rules have been challenged and may change again. We confirm the current terms with you before you apply. Net metering vs net billing explained →


Under the old system, one exported unit cancelled one imported unit. Under net billing, the two are valued differently:
Your bill = units you import × your K-Electric tariff − units you export × the buyback rate
Because exported units now earn much less than imported units cost, the units you use directly from your panels are worth far more than the units you send to the grid.
For example, if your panels produce 600 units in a month and you use 400 of them during the day, those 400 units save you the full K-Electric tariff, while the 200 exported units earn only the lower buyback rate. That is why we size every system around your daytime load and show you the expected bill before installation.
Yes, for most homes and businesses, but the way systems are designed has changed. Net metering in Karachi now works best when:
Solar still pays off because K-Electric tariffs are high and panels now cost far less than a few years ago. A system sized for self-use pays back faster than one built mainly to export, and it keeps cutting your bill for 20 to 25 years. Homes with heavy daytime AC use, and offices, schools, shops and factories that work in daylight, see the strongest returns. Customers with an older net metering agreement also keep their existing terms until it expires.
We design every system for self-consumption first, so net metering adds value rather than being the main source of savings. Is solar worth it →

Send your K-Electric bill on WhatsApp or call 0311-7443116. We reply with the right system size and an itemised quote.
Our net metering service covers every step K-Electric requires:
we confirm your system fits within your sanctioned load and advise if regularisation through your K-Electric IBC is needed first.
K-Electric net metering process →We check that the name and address on the owner’s CNIC match the latest K-Electric bill, and that your sanctioned load suits the system size, before the file goes in.
Open in Google Maps →The vendor checklist, PPIB vendor certificate, inverter data sheet and inverter settings, prepared by our team so your net metering file is complete.
How to choose a solar company →We submit your net billing file on K-Electric’s online portal, respond to any queries and track its status through review, inspection and approval.
Solar panel installation in Karachi →we resolve any discrepancies K-Electric raises during qualification and technical review.
Solar system for home in Karachi →We guide you through the agreement, estimate and payment. K-Electric's demand notice and meter costs are explained before you pay.
Solar calculator Karachi →we follow up until K-Electric installs and activates your green meter.
Solar panel tilt angle in Karachi →we review your first net billing bill with you to confirm exports are recorded correctly.
Solar system size guide →Every application for net metering in Karachi follows the same basic stages, according to K-Electric's April 2026 net billing guidelines:
Applications are processed by PPIB pre-qualified vendors on the customer's behalf, so your installer's pre-qualification matters.
Your vendor submits the application and documents on K-Electric's website, and you receive a case ID to track it.
K-Electric qualifies the case within 5 working days, if all prerequisites are met.
K-Electric reviews the case within 15 working days, following PPIB guidelines.
For qualified cases, the agreement and estimate are completed within 14 working days.
You pay the estimate within 7 working days.
K-Electric installs and activates the bidirectional meter within 15 working days of payment confirmation.
For the full document list and timelines, read our net metering process guide.
The green meter is a bidirectional meter that records both the units you import from K-Electric and the units you export. K-Electric installs it after approval and payment. We coordinate the installation and check that both readings appear correctly on your bill.
Most delays we see are avoidable:
Checking these before submission is the fastest way to get net metering in Karachi approved.
If your agreement was signed before 9 February 2026, your existing terms continue until it expires. Adding panels, changing your system or renewing your agreement may bring you under the new rules, so check with us before making changes.
Rooftop solar installation process →Commercial and industrial customers apply under the same net billing rules, but larger systems need more documentation: incorporation documents and an NTN, and an EIK NOC and approved load flow study above 250 kW.
Commercial solar installation in Karachi →Most homes apply for net billing with a correctly sized on-grid or hybrid system, so daytime solar units cut the bill and surplus units are exported to K-Electric. Hybrid systems add battery backup for load shedding, and we size every system from your bill units.
Home solar panels for Karachi houses →The cost of net metering in Karachi includes the generation licence fee, which K-Electric lists as Rs 1,000 per kW and is paid by pay order, plus the meter replacement cost, which the applicant pays. Our application handling fee is confirmed in your written quote. Your quote shows these costs separately.
Net metering in Karachi lets a solar system owner export surplus electricity to K-Electric through a bidirectional meter. Since February 2026, new applicants are on net billing, where exported units are credited at a lower buyback rate.
Yes, K-Electric still accepts applications, but new connections are processed under net billing rather than the old one-to-one net metering.
K-Electric reviews and approves applications in Karachi under NEPRA's regulations, after qualification and technical review. K-Electric also applies to NEPRA for the generation licence on your behalf.
K-Electric's stated turnaround times add up to about 56 working days if each stage uses its full allowance, and longer if documents or the site have problems. We track your file and keep you updated at each stage.
Yes, after we inspect the system. If the wiring, protection or earthing does not meet requirements, we fix it before applying. Solar repair →
Yes. K-Electric's guidelines require a PPIB vendor certificate, and applications are processed by PPIB pre-qualified vendors.
Send us your latest K-Electric bill and your system details. We will check your eligibility, confirm the current rules and tell you exactly what your application needs.