Net Metering in Karachi: K-Electric Net Billing, Handled for You

Solar Installation Karachi handles net metering in Karachi from start to finish. We check your sanctioned load, design your system to fit the current rules, prepare your documents, submit the application to K-Electric, follow it through review and track it until your bidirectional meter is installed.

Last reviewed: October 2026

Important: Net Metering Is Now Net Billing

In February 2026, NEPRA replaced the old net metering rules with the Prosumer Regulations 2026. K-Electric now processes new applications as net billing. Most people still call it net metering in Karachi, so we use both terms on this page.

For new applicants, the main changes are:

  • Exported units are credited at a buyback rate set by NEPRA, which is much lower than the rate you pay for imported units.
  • Imported units are billed at your normal K-Electric tariff.
  • New agreements run for five years, shorter than before.
  • System capacity is limited to your sanctioned load.
  • Customers who signed a net metering agreement before 9 February 2026 continue under their existing terms until the agreement expires.

These rules have been challenged and may change again. We confirm the current terms with you before you apply. Net metering vs net billing explained →

Rooftop solar panels connected to the K-Electric grid under net billing in Karachi
Net billing since February 2026
Calculating a K-Electric bill under net billing with imported and exported solar units
Self-use saves the most

How Net Billing Affects Your K-Electric Bill

Under the old system, one exported unit cancelled one imported unit. Under net billing, the two are valued differently:

Your bill = units you import × your K-Electric tariff − units you export × the buyback rate

Because exported units now earn much less than imported units cost, the units you use directly from your panels are worth far more than the units you send to the grid.

For example, if your panels produce 600 units in a month and you use 400 of them during the day, those 400 units save you the full K-Electric tariff, while the 200 exported units earn only the lower buyback rate. That is why we size every system around your daytime load and show you the expected bill before installation.

Is Net Metering Still Worth It in Karachi?

Yes, for most homes and businesses, but the way systems are designed has changed. Net metering in Karachi now works best when:

  • Your system is sized to match your daytime use, not oversized to export.
  • Heavy loads such as ACs, pumps and machinery run during daylight hours where possible.
  • A hybrid system with batteries stores surplus daytime power for evening use, where the budget allows.

Solar still pays off because K-Electric tariffs are high and panels now cost far less than a few years ago. A system sized for self-use pays back faster than one built mainly to export, and it keeps cutting your bill for 20 to 25 years. Homes with heavy daytime AC use, and offices, schools, shops and factories that work in daylight, see the strongest returns. Customers with an older net metering agreement also keep their existing terms until it expires.

We design every system for self-consumption first, so net metering adds value rather than being the main source of savings. Is solar worth it →

Solar panel being installed for a Karachi home where net metering is still worth it
Designed for self-use first

Get a Free Solar Site Survey in Karachi

Send your K-Electric bill on WhatsApp or call 0311-7443116. We reply with the right system size and an itemised quote.

K-Electric Net Metering Process: Step by Step

Every application for net metering in Karachi follows the same basic stages, according to K-Electric's April 2026 net billing guidelines:

01

Choose a qualified installer

Applications are processed by PPIB pre-qualified vendors on the customer's behalf, so your installer's pre-qualification matters.

02

Apply online

Your vendor submits the application and documents on K-Electric's website, and you receive a case ID to track it.

03

Qualification

K-Electric qualifies the case within 5 working days, if all prerequisites are met.

04

Technical review

K-Electric reviews the case within 15 working days, following PPIB guidelines.

05

Agreement and estimate

For qualified cases, the agreement and estimate are completed within 14 working days.

06

Payment

You pay the estimate within 7 working days.

07

Meter installation

K-Electric installs and activates the bidirectional meter within 15 working days of payment confirmation.

For the full document list and timelines, read our net metering process guide.

Green Meter Installation in Karachi

The green meter is a bidirectional meter that records both the units you import from K-Electric and the units you export. K-Electric installs it after approval and payment. We coordinate the installation and check that both readings appear correctly on your bill.

Why Net Metering Applications Get Delayed or Rejected

Most delays we see are avoidable:

  • Sanctioned load on the bill does not match the system size
  • Name or address on the bill does not match the applicant's CNIC
  • Earthing issues found during review
  • Panels installed do not match the panels in the application
  • Installation still in progress when the case is reviewed
  • Roof ownership that cannot be confirmed, for example on rented property

Checking these before submission is the fastest way to get net metering in Karachi approved.

How Much Does Net Metering Cost?

The cost of net metering in Karachi includes the generation licence fee, which K-Electric lists as Rs 1,000 per kW and is paid by pay order, plus the meter replacement cost, which the applicant pays. Our application handling fee is confirmed in your written quote. Your quote shows these costs separately.

Net Metering FAQs

What is net metering in Karachi?

Net metering in Karachi lets a solar system owner export surplus electricity to K-Electric through a bidirectional meter. Since February 2026, new applicants are on net billing, where exported units are credited at a lower buyback rate.

Is net metering still available in Karachi?

Yes, K-Electric still accepts applications, but new connections are processed under net billing rather than the old one-to-one net metering.

Who approves net metering in Karachi?

K-Electric reviews and approves applications in Karachi under NEPRA's regulations, after qualification and technical review. K-Electric also applies to NEPRA for the generation licence on your behalf.

How long does net metering approval take in Karachi?

K-Electric's stated turnaround times add up to about 56 working days if each stage uses its full allowance, and longer if documents or the site have problems. We track your file and keep you updated at each stage.

Can you apply for net metering on a system another company installed?

Yes, after we inspect the system. If the wiring, protection or earthing does not meet requirements, we fix it before applying. Solar repair →

Do I need a PPIB pre-qualified installer?

Yes. K-Electric's guidelines require a PPIB vendor certificate, and applications are processed by PPIB pre-qualified vendors.

Get Help with Net Metering in Karachi

Send us your latest K-Electric bill and your system details. We will check your eligibility, confirm the current rules and tell you exactly what your application needs.

Talk to us directly

Request a Free Survey

Sends your details to us on WhatsApp.