– K-Electric now processes new applications as net billing under NEPRA’s Prosumer Regulations 2026, but most people still call it net metering.
Key takeaways
Most delays in the K-Electric net metering process start before the application is even submitted. Check these first:

The name and address on the owner’s CNIC must match the latest K-Electric bill, and any mismatch has to be corrected before you apply for net metering.
Net metering in Karachi →your connected load must match the sanctioned load on your bill. If it does not, you must regularise it through your K-Electric IBC before applying.
Solar system size guide →your installer must be a PPIB pre-qualified vendor, because the vendor processes the application on your behalf.
How to choose a solar company →K-Electric’s guidelines list the documents below. Which ones you need depends on whether you are applying as a household, a company, or a mosque, trust or similar organisation. Check K-Electric’s latest application form before submitting, as requirements can change.
| Step | What happens | K-Electric’s stated time |
|---|---|---|
| 1. Apply online | Your vendor fills in the application on K-Electric’s website and uploads the scanned documents | At submission |
| 2. Case ID | You receive a provisional case ID and login details by SMS and email to track status online | At submission |
| 3. Qualification | K-Electric qualifies the case, provided all prerequisites are met | Within 5 working days |
| 4. Technical review | Initial and technical review following PPIB guidelines; discrepancies are notified to your vendor within 3 working days | Within 15 working days |
| 5. Agreement and estimate | Agreement signing and estimate for qualified cases | Within 14 working days |
| 6. Payment | Pay online or at a partner bank | Within 7 working days of the estimate |
| 7. Meter and activation | Bidirectional meter installed and connection activated | Within 15 working days of payment confirmation |
K-Electric also applies to NEPRA for the generation licence on your behalf.
If every stage takes its full allowance, the stated turnaround times add up to about 56 working days from a complete application to meter activation. K-Electric notes that this can take longer when documents are incomplete, when there are problems on site, or when the local transformer needs upgrading at the customer’s cost.
K-Electric’s guidelines say a case can be rejected for reasons such as:
Delays also come from name or address mismatches, unregularised load, incomplete vendor paperwork and transformer capacity limits. K-Electric can also review systems later and terminate connections for problems with quality, capacity, design or the inverter, so a properly engineered installation matters beyond approval day. Solar safety guide →
Listed by K-Electric as Rs 1,000 per kW of system size, paid by pay order as part of your net metering application, so a 10 kW system pays about Rs 10,000.
Solar system price in Karachi →The cost of the new bidirectional (green) meter is borne by the applicant, in addition to the licence fee and any documentation charges.
Solar panel installation in Karachi →As issued by K-Electric for your case, covering items such as the meter and any work needed at your connection.
Green meter application help →Whatever your installer charges for preparing documents, submitting the file and managing it through K-Electric review and inspection.
Spot genuine tier-1 panels →K-Electric also publishes a self-procured meter policy for customers who want to buy their own meter.
Each meter on the property is treated as a separate net metering case, with its own application, sanctioned load and solar system size.

roof ownership must be confirmed, so you will need the owner’s documents and consent.
Solar for apartments in Karachi →the system must meet NEPRA and PPIB standards, including earthing and correctly matched panels, before it can be approved.
Net metering vs net billing →K-Electric’s net metering desk is at the KE Wing, Ground Floor, Civic Center, open Monday to Friday during office hours. Queries can also be emailed to K-Electric’s net metering address listed on its website.
For a home, the main documents are the owner’s CNIC, the latest K-Electric bill with matching name and address, the vendor checklist and PPIB certificate, the inverter data sheet and settings, and a pay order for the generation licence fee.
Through a PPIB pre-qualified vendor, who submits your application and documents on K-Electric’s online portal. You then track the case with the login details K-Electric sends you.
K-Electric’s stated turnaround times add up to about 56 working days if each stage uses its full allowance, and longer if documents or the site have problems.
K-Electric’s guidelines state that the applicant bears the meter replacement cost.
New applications are processed as net billing under NEPRA’s Prosumer Regulations 2026, but K-Electric and most customers still use the term net metering. Net metering vs net billing explained →